Kerbready London › Barking and Dagenham

Dropped kerb in Barking and Dagenham: cost, rules and approval checklist

Checked against Barking and Dagenham Council's policy and website on 19 November 2026

Barking and Dagenham lets you pay for a dropped kerb in instalments, and it allows angled parking on shallower front gardens. It will not approve a crossover that removes on-street parking, including a bay in a CPZ.

This page covers homes in Barking, Dagenham, Becontree and Chadwell Heath. The council's contractor builds every crossover. You must finish your hardstanding and drainage first, and tell the council when it is done.

The rules at a glance

Parking space

For parking straight in: 4.5m clear from the footpath to the building and 2.4m wide. Angled parking can work from 3.8m deep on a wider frontage. Nothing is approved under 3.8m.

Angled parking widths

The shallower the garden, the wider it must be: 3.8m deep needs 6m wide, 4.0m needs 5.7m, 4.2m needs 5.5m and 4.4m needs 5.2m.

Crossover width

3.6m at the kerb including the sloping kerbs, narrowing to 2.7m at the back of the pavement. One crossover per front garden; leave 300mm of level kerb between yours and a neighbour's.

Street trees

No crossover within 1m of a tree base, so the tree must stand at least 4.6m from your boundary. Trees are not normally removed, and the arboricultural officer's decision is final.

Controlled parking zones

Refused if the crossover would remove or reduce on-street parking, including a bay in an existing CPZ.

Hazards

Generally not approved close to junctions, school entrances, crossings, bus stops, bends or traffic calming. A crossover cannot overhang a road hump.

What a dropped kerb costs in Barking and Dagenham

Do you need planning permission?

Usually not for a house. You are likely to need it if:

Hardstanding must be solid: unbound gravel is not accepted, and it must not drain onto the pavement. Gates must not open outwards over the footway.

How long it takes

The council aims to send a quotation within four weeks of your application and to install within 12 weeks, subject to conditions. Once you have paid, or agreed an instalment plan, construction is within eight weeks. Quotes last three months.

If you are refused

Refused applicants can appeal through the council's website. Blue Badge holders may get exceptional consideration.

Before you pay the application fee

  1. Measure from the footpath to the building: 4.5m for straight-in parking, or check the angled-parking table if you are between 3.8m and 4.5m.
  2. Measure from your boundary to the nearest street tree: it must be at least 4.6m away.
  3. Look at the road outside: if your crossover would take a parking space or CPZ bay, it will be refused.
  4. Check for junctions, school entrances, crossings and bus stops nearby.
  5. Lay solid, properly drained hardstanding before the council will build.

How Barking and Dagenham compares with its neighbours

CouncilApplication feeMinimum parking spaceStreet tree rule
Havering£261Not publishedRefused within 1m of a tree
Newham£250Not publishedNot published
Redbridge£438Not publishedMature trees protected

Related guides